Scottsdale Road Moves Onto Its New Pavement This Week, and Dynamite Reopens Next

The Wednesday-night switch on Scottsdale Road was scheduled to move traffic onto fresh asphalt on the east side of the corridor, from Jomax Road north to Dixileta Drive. Today, crews are scheduled to start final paving on the west side. If the City of Scottsdale's schedule holds, Dynamite Boulevard reopens to east- and westbound traffic on both sides of Scottsdale Road just before Thanksgiving, and the whole project wraps up in late December.

That December finish comes about six months after the date the city first gave. City spokeswoman Holly Peralta told the Scottsdale Progress that switching the Dynamite intersection from a roundabout to a traffic signal is what added the time. So the next few weeks are when that choice finally shows up on the road. Here's the order things open back up, what the decision cost by each side's count, and what the corridor looks like when the cones come down.

Where the lanes sit this week

Until the overnight change on Wednesday, Nov. 18, Scottsdale Road ran on its west side, one lane each way, between Dixileta and Jomax. Dynamite Boulevard, Oberlin Way and Bent Tree Drive were all closed on the east side so crews could rebuild that half of the intersection. The overnight change was set to reopen the east side of Scottsdale Road at those three streets and move through traffic onto the new pavement.

West-side final paving runs Nov. 19 through 25. It starts at Dixileta and works south toward Jomax. Three details matter this week if you drive the corridor every day:

  • No northbound left turns into Pinnacle Vista Drive or Bobwhite Way while west-side paving is underway. If you usually make one of those turns heading home, plan to come in from another direction until the 25th.
  • The west side of the Dixileta intersection is closed on Nov. 19 for paving.
  • Short stops at side streets as the paver crosses each one. Law enforcement is scheduled to be on site to help direct traffic.

The speed limit through the construction zone is still 30 mph. Work is mostly on weekdays during the day, but the city has said nights or weekends may be needed at times.

East-side final paving was scheduled for Nov. 11 through 18, with a one-day closure on the east side of Dixileta on Nov. 16. Members of Desert Foothills Lutheran Church had a temporary driveway setup scheduled through Nov. 18. The driveway across from Bobwhite Way was exit only, and the south driveway was enter only, while crews built the median island at Bobwhite.

What reopens when, from now to late December

Each step below depends on the one before it. Dynamite can't reopen until the west side is paved, and striping can't start until utilities are raised to the new surface. These are the city's scheduled dates as of its Nov. 1 update:

  1. Nov. 19–25: Final paving on the west side, moving south from Dixileta. No northbound left turns into Pinnacle Vista Drive or Bobwhite Way.
  2. Just before Thanksgiving: Dynamite Boulevard reopens on both sides of Scottsdale Road for east- and westbound traffic.
  3. Week of Nov. 30: Crews raise utilities to sit flush with the new asphalt, prepare for striping, and finish landscaping and punch-list items. Lane reductions continue, but traffic will be on the correct side of the median.
  4. Late December: The project is scheduled to be complete.

Step three is the one that will change your drive the most. Construction began in December 2024, and the November schedule has traffic shifted to one side of the road. Once the week of Nov. 30 arrives, northbound and southbound traffic will be on their own sides of the new median, even with fewer lanes open. The city's project page says final paving and striping come at the very end of the project.

The city's project info line is 480.898.4110, and the project page is the official record if any of these dates move.

Why the finish line moved from summer to December

When the original roundabout version of the project was approved, the city told the Scottsdale Progress that construction would start in November and finish in summer 2026. The schedule changed on April 8, 2025. That night the City Council voted 4–3 to redesign the Scottsdale Road and Dynamite Boulevard intersection as a traffic signal instead of the planned roundabout, according to the approved council minutes.

The Daily Independent's report on the vote described residents on both sides. Some North Scottsdale residents opposed the roundabout, including people worried about pulling horse trailers through it. Council members also gave different counts of where residents stood. Opponents of the switch pointed to a city staff report. That report said the intersection had seven crashes from 2015 through 2019, five of them with incapacitating injuries, and it cited national findings that roundabouts reduce injury crashes.

The redesign had to be engineered after the vote, and the signal work at Dynamite began in early 2026. Peralta laid out the effect on the schedule in the Progress:

"The change from the roundabout design to a signalized intersection did result in additional design work and extended the overall project timeline by approximately six months."

That's why the east half of the Dynamite intersection was still being rebuilt in November. The rest of the corridor was described as nearing completion back in spring. At the May 21, 2026 Transportation Commission meeting, city staff said Scottsdale Road from Jomax to Dixileta was nearing completion and expected to finish by fall 2026.

What the signal decision cost, by each side's account

Money became the second argument. Before the vote, city engineer Alison Tymkiw's report warned that the change in scope would mean giving up $31,132,929 in federal funding. It also said the city might be able to swap that money for regional funds through the Maricopa Association of Governments. Here is how the figures reported since then line up:

Figure What it represents Reported by
$13.9 million Original project budget, set in 2019 Daily Independent
$43,685,237 Approved project budget, unchanged after the redesign City of Scottsdale
$29.29 million Regional Proposition 400 funding MAG approved to replace the federal share Scottsdale Progress
$1.8 million Forfeited federal safety grant, replaced with the city's 0.1% Transportation Sales Tax, per the city Scottsdale Progress
$3.4 million Added cost of the redesign, according to Mayor Lisa Borowsky's office Scottsdale Progress
$4.14 million Added cost, paid from contingency and unused construction-administration funds, leaving $850,000 in reserves Daily Independent

The city's position, as Peralta put it to the Progress, is that the project stays within its approved $43.7 million budget and that funding for the corridor was preserved. The Daily Independent's numbers point the same way: the project stays on budget, but by spending most of its cushion. Every figure in the table is about the same two-mile stretch of road. The largest gap in the table is between the $13.9 million budget set in 2019 and the $43.7 million approved in 2024 for what the city calls a complete street.

What the finished corridor adds to your routine

According to the city's project page and FAQ, the finished road between Jomax and Dixileta includes:

  • Landscaped medians, with left-in/left-out median islands at Bobwhite Way and Pinnacle Vista Drive
  • A HAWK crossing at Pinnacle Vista Drive, a pedestrian signal that is activated when someone wants to cross
  • A 10-foot concrete shared-use path on the east side and an 8-foot separated sidewalk on the west side
  • 5-foot bike lanes
  • Unpaved trails on both sides, built after the roadway work
  • Drainage improvements meant to eliminate at-grade wet crossings, where water crosses the road surface

The median islands at Bobwhite and Pinnacle Vista are the change to learn now. The temporary turn bans end with paving, but the permanent islands will shape how you turn in and out of those streets long after the cones are gone. The drainage work is aimed at storms that send water across the road. The east-side path, the bike lanes and the trails give people on foot and on bikes their own space along this stretch of Scottsdale Road, and the Pinnacle Vista HAWK gives them a signal-controlled place to cross.

For North Scottsdale hikers, our Brown's Ranch trailhead post covers trailhead parking this season, and our North Scottsdale neighborhood page covers the rest of the area.

If you're weighing a home off Dynamite, Pinnacle Vista or Bobwhite, or deciding when to list one, the turn rules and the December finish are the details that come up at showings this winter. I'm glad to talk through how the new corridor fits your plans. Reach out to Wendy O Real Estate and let's connect.

Work With Wendy

Wendy Ortiz brings deep Valley market knowledge, strategic negotiation, and a personalized approach to every transaction. From first-time buyers to luxury sellers and investors, she delivers expert guidance and a seamless experience tailored to each client’s goals.

Follow Me on Instagram